Directorate of Strategic Planning and Monitoring

01942461493
ppmo@skuastkashmir.ac.in, drnazirahmad@gmail.com

 

LANGUISHING under CAPEX

 

Year

works

Allotment

Released

Expenditure

Works Completed

2018-19 & 2019-20

7

221445

1102.79

1102.79

03

 

Languishing Projects 2018-19

 

Sanctioned in 6th Meeting of the High Powered Committee Meeting held on ……….,Constituted Vide order No281-PD of 2018 dated 08-09-2018

S.No.

Name of Project/Work

LUP CODE

Amount Sanctioned

Amount Released

Expected date of completion

01

Construction of Girls Hostel Wadura Sopore

LUP1645

360.00

308.22

Completed and inaugurated

02

Construction of Girls Hostel RangilGanderbal

LUP1646

415.00

188.22

 

03

Construction of Girls Hostel Benehama

LUP1647

415.00

93.73

 

04

Construction of Symposium at Main campus

LUP1648

261.89

0.00

 

05

Construction of Girls Hostel at ShuhamaAlustang

LUP1649

280.00

235.63

Completed and inaugurated

06

Construction of Girls Hostel at Shalimar

LUP1650

285.00

206.34

Completed and inaugurated

07

Construction of Lab cum Office Block B, at Shalimar

LUP1651

105.650

70.65

Completed and inaugurated

 

 

 

2122.54

1102.79